Workbench/bar
September 23, 2021 The latest project is a workbench/bar. I used old lumber and boards that had been under our place for years. It took some work to clean them up and they still didn’t want to fit together very well. But with Karla’s help we got them to stick and I think they will…
-
Electric is done
August 4, 2021 I should post a video of both garage doors moving.The lights are on and the water is running. We are letting the water run for a while and we will get it tested. But that is it for the contractors. The rest is up to us.I put the door on the bathroom.…
-
July
July 27, 2021 Almost a month has gone by without any posts. I knew I would get behind. But I’m the only one here so it doesn’t really matter. July was busy. Pole Building:– A lot of the plumbing went in. However, the water heater is on back order.– The sink is hooked up by…
-
Making Progress
July 4, 2021 Septic is in. Bathroom ready for plumbing. Both garage doors and openers. Electric almost done.
-
More work
June 30, 2021 Railings for the addition and a well for the pole building. I put this together June 17, but I guess I didn’t publish it. Here it is. Look for another post tomorrow.
-
more work
June 5, 2021 Major construction of the pole building is complete. There are still a lot of projects to complete. Doors, electric, well and pluming just to name the big ones. The addition is progressing. We are a little behind schedule, but hope to make it up today.
-
Two Projects
June 4, 2021 The pole building is moving full speed and the major construction is almost done. Because that is not enough, we have started an addition on our home. Watch the Flickr albums for updates.
-
Pole Building
May 12, 2021 I’ve been meaning to add something here, but the days keep slipping by. It has been a little cold, so mostly we just work and stay inside. We have had some nice days and almost everything is ready for summer. The big adventure is the construction of our pole barn. They have…